Castries, April 13, 2018 – The St. Lucia Electricity Services Limited (LUCELEC) 3MW Solar Farm in La Tourney, Vieux Fort is now feeding solar energy into the island’s electricity grid. Energy from the nearly 15 thousand solar panels that comprise the island’s first utility-scale solar farm began feeding the grid on Monday, April 9, and the entire 3 megawatts was online on Wednesday, April 11.

Project Director, LUCELEC’s Acting Planning Manager Cornelius Edmund, is pleased that the energising tests have gone well and the solar farm is producing its maximum output.

“The project is about 90% complete. All the panels and associated electrical works have been installed and tested. The contractor is currently putting the finishing touches such as communication and security equipment, completing the fencing, drainage and service-road works and site clean-up.   They’re also conducting all the pre-commissioning tests. We want to ensure that everything is working as it should before the project is commissioned and handed over to LUCELEC,” he explained.

Related Post

All of this should be completed by mid-June. The main contractor for the solar farm is GRUPOTEC, an international firm with extensive experience in developing solar plants worldwide. But in the design of the project and the contract, LUCELEC ensured there were provisions for local labour resulting in three sets of local contractors and 40 to 45 people hired for transfer of knowledge and technology.

Construction of the 20-million-dollar renewable energy project funded by LUCELEC started in November 2017. The panels are spread across three sites distributed over a total of 15 acres of land, just north of the Hewanorra International Airport.

The 3 megawatt solar farm will generate 7 million kilowatt-hours (or units) of electricity per year, which is about 1.3% of the electricity generated from LUCELEC’s Cul De Sac Power Plant. It will reduce the annual volume of fuel purchased by LUCELEC by about 300 thousand gallons. LUCELEC uses approximately 19 million gallons of fuel per year.

Tags: lucelecsolar
Press Release

Recent Posts

Would Be Robber Shot Dead in Corinth

The male was later identified as thirty -three (33) year old Ted Smith of Mon Repos, Micoud was transported to… Read More

16 hours ago

Machine Guns No Match For A Match!

In recent dispatch to a writer friend from our days of California dreaming (several years ago he too had… Read More

1 day ago

Vincent Edmunds St. Omer Obituary

Dr. Vincent Victor Edmonds St. Omer, 89, of Columbia, passed away on Tuesday, July 25, 2023. He was born on… Read More

7 days ago

At long last, shepherd not afraid to take risks in the interest of his flock!

The in-depth comment coming from Archbishop Gabriel Malzaire is most commendable.  It's good to have in the seat of local religious… Read More

7 days ago

Wall of China Can’t Touch Helen’s Bam-Bam” Wall!

"The Bum Bum Wall is disgrace and these women should be ashamed of themselves, no pride, no respect for… Read More

1 week ago

18 Year Old Arrested for Murder

The male was later identified as Scott Chester Louison twenty (20) years old of Morne Du Don, Castries Read More

2 weeks ago

This website uses cookies to improve your experience. No personally identifiable information is stored.